Dongguan Qingxi · 1 MW / 2 MWh C&I BESS Supply

Dongguan Qingxi · 1 MW / 2 MWh C&I BESS Supply

LFP 280 Ah · 125 kW PCS · 3-level BMS + EMS + fire suppression · 50 days lead time

CASE STUDY · C&I ENERGY STORAGE SUPPLY

1 MW / 2 MWh C&I BESS Equipment Supply, Dongguan Qingxi

Equipment supply for a 1 MW / 2 MWh peak-shaving / valley-filling C&I energy storage station in Qingxi, Dongguan. The package covers LFP cells, 125 kW PCS, 3-level BMS, local and cloud EMS, plus complete fire-suppression and safety subsystems — delivered with FAT report, on-site supervision and commissioning.

Project Location
Qingxi, Dongguan, Guangdong
Project Type
C&I Peak-Shaving / Valley-Filling Storage
Storage Configuration
1 MW / 2 MWh
Delivery Scope
Equipment Supply · FAT Report · On-Site Supervision · Commissioning
Lead Time
50 days from contract signing to factory delivery

Core Equipment List

BatteryLFP 280 Ah cell · 1P416S configuration
PCS125 kW bi-directional energy storage converter
BMS3-level BMS (slave + master + system)
EMSLocal EMS + cloud-based monitoring APP
Fire ProtectionPerfluoroketone (Novec-equivalent) fire suppression + combustible gas detection + explosion-vent panels

On-Site Photos

Storage cabinet, installation and on-site delivery

On-site deliveryStorage cabinetInstallation

Core Highlights

Highlight 1

Modular Design · Parallel Cabinet Expansion

Each storage cabinet is a self-contained module. Multiple cabinets can be paralleled to scale capacity — the same architecture supports anything from a single cabinet to MWh-scale stations.

Highlight 2

Pre-Configured Peak/Valley Arbitrage Strategy

The EMS ships with a pre-configured time-of-use peak / valley arbitrage strategy — the client only needs to power on, and the system begins earning revenue immediately.

Highlight 3

Factory Cycle-Tested · Plug-and-Play On Site

Every cabinet completes full charge / discharge cycle testing before shipping. The on-site team only needs to position the cabinet and connect cables — true plug-and-play deployment.

Delivery Capability

Phase-by-phase deliverables and timeline

PhaseDeliverableDuration
Solution ConfirmationConfirm project specification and BoM5 days
ProductionManufacturing order placed and cabinets produced40 days
On-Site CommissioningLogistics to site, installation and commissioning5 days