Huizhou Boluo · PV-Storage-Charging Demonstration Station

Huizhou Boluo · PV-Storage-Charging Demonstration Station

600 kWp BIPV canopy + 125 kW / 261 kWh storage + 11 chargers · 60 days to grid

CASE STUDY · PV + STORAGE + CHARGING

PV-Storage-Charging Integrated Demonstration Station, Huizhou Boluo

A full-stack public fast-charging station that combines a 600 kWp BIPV solar canopy, a 125 kW / 261 kWh LFP battery system and 11 chargers (3 × 60 kW DC fast + 8 × 7 kW AC), all controlled by a single EMS — delivered turnkey from design to grid in 60 days.

Project Location
Boluo, Huizhou, Guangdong
Project Type
Public Fast-Charging Station · PV + Storage + Charging
PV Configuration
600 kWp BIPV Solar Canopy
Storage Configuration
125 kW / 261 kWh LFP Battery System
Charging Configuration
3 × 60 kW DC dual-gun fast chargers + 8 × 7 kW AC chargers
Grid Connection
0.38 kV MV grid-tie
Design → Grid Cycle
60 days

On-Site Photos

Steel-structure installation and finished PV canopy

Steel-structure installationFinished PV canopy

Core Highlights

Highlight 1

Green-Energy Self-Sufficient Operation

Built on a public-institution parking lot: PV directly supplies the chargers during the day with surplus stored in batteries; the storage discharges at night to power the chargers — a fully green-energy self-sufficient operating model.

Highlight 2

~¥80,000 / Year Electricity Savings

By feeding PV power directly to the chargers, the station saves roughly ¥80,000 per year in electricity costs for the local government — improving both economic returns and operational ESG metrics.

Highlight 3

EMS Unified Control · Drawings Approved on First Submission

A unified EMS platform controls all three sides — PV, storage and chargers. The full set of drawings passed the grid utility's technical review on first submission, accelerating the project schedule.

Delivery Capability

Phase-by-phase deliverables and timeline

PhaseDeliverableDuration
Solution DesignSite survey · PVsyst yield simulation · Storage sizing · Charging-load calculation7 days
Drawing & ApprovalAutoCAD electrical / structural drawings · Grid application · Utility approval15 days
Equipment IntegrationPV modules, BESS and chargers — unified procurement and factory test8 days
Construction & GridInstallation, commissioning, EMS integration, grid connection and handover training30 days