Shenzhen Guangming · 600 kW C&I Rooftop PV

Shenzhen Guangming · 600 kW C&I Rooftop PV

UAV mapping + 3D rendering + full drawing package · 20 days survey-to-issue

CASE STUDY · ROOFTOP PV DESIGN

600 kW C&I Rooftop PV Design with 3D Rendering, Shenzhen Guangming

A 600 kWp C&I rooftop PV project for a Guangming client. We delivered the full design package — UAV aerial mapping, photorealistic 3D rendering, shading analysis, cable-routing optimization and a complete CAD drawing set — within 20 days from site survey to issued drawings.

Project Location
Guangming, Shenzhen, Guangdong
Project Type
C&I Rooftop PV
PV Configuration
600 kWp Rooftop PV
Grid Connection
0.38 kV LV grid-tie
Survey → Drawing Cycle
20 days

3D Effect Rendering

UAV aerial mapping + 3D modeling — true-to-site preview of the finished PV installation

600 kW rooftop PV 3D render

Design Drawings

Module layout, cable routing, electrical interconnection and structural details

Design drawing — PV layout / electrical / structuralDesign drawing detail

Core Highlights

Highlight 1

UAV Aerial Mapping · True-to-Site 3D Rendering

Drone aerial photography is used to build an accurate 3D model of the rooftop, which is then rendered to show the finished PV installation effect — giving the client a clear preview before construction starts.

Highlight 2

Precise Shading Analysis · Optimized Cable Routing

Detailed shading analysis on the 3D model plus optimized DC/AC cable routing minimize material usage and reduce overall plant construction cost.

Highlight 3

Fast Response · Accurate Drawing Output

From site survey to issued drawings in 20 days. The deliverable package covers module layout, cable routing, electrical interconnection and structural details — ready for procurement and construction.

Delivery Capability

Phase-by-phase deliverables and timeline

PhaseDeliverableDuration
Site SurveyRooftop conditions · Cable routing · Power-room configuration1 day
3D RenderingPV layout 3D render · Cable routing diagram4 days
Design DrawingsPV module layout · Cable routing · Electrical interconnection · Structural details15 days