SJ Solarhub logo
SJ Solarhub
0.36 MWp BIPV Solar Canopy · Dongguan

0.36 MWp BIPV Solar Canopy · Dongguan

Commercial BIPV Solar Canopy · Detailed Engineering Design & Grid Interconnection Approval

Commercial BIPV Solar Canopy · Detailed Engineering Design & Grid Interconnection Approval

0.36 MWp Distributed PV Project · Dongguan, China
May 2025 – July 2025Dongguan, Guangdong0.36 MWp · 60 Days to Gridwww.sjsolarhub.com
SECTION I.

Project Overview

ParameterValue
System Capacity0.36 MWp (588 × 615 Wp Bifacial Double-Glass Modules)
Inverter Solution3 × Huawei SUN2000-110KTL-M2 (110 kW String Inverters, 330 kW Total)
Mounting TypeBIPV Waterproof Solar Canopy
LocationDongguan, Guangdong, China
Design PeriodMay 2025
Commissioning DateJuly 2025
Design-to-Grid Timeline60 Days (Design → Approval → Construction → Grid Connection)
Est. Annual Yield (Year 1)~380,000 kWh (379,683 kWh)
CO₂ Reduction (Year 1)~217 Tons / Year
SECTION II.

Design Scope

This project demonstrates SJ Solarhub's end-to-end design capability—from site survey to full detailed drawing package and grid interconnection approval. Our design team holds national-grade new energy design qualifications and is familiar with the technical standards of major utility companies in China and overseas, ensuring drawings pass review on the first submission.

Site Survey & Multi-System Assessment

Beyond roof structure measurement, we conducted detailed surveys of the existing electrical distribution system and cable routing in the distribution room. We assessed PV interconnection point compatibility and capacity margins, providing precise inputs for subsequent drawing design.

Roof structure survey · distribution-system survey · cable-routing assessment
Roof structure survey · distribution-system survey · cable-routing assessment

UAV Aerial Survey & 3D Modeling

High-resolution orthophoto captured by drone, combined with on-site measurement data, imported into professional software for 1:1 three-dimensional modeling. Precise simulation of module layout, shadow occlusion, and steel structure load distribution.

UAV Aerial Photography
UAV Aerial Photography
Steel-structure 3D modeling
Steel-structure 3D modeling
Module + steel-structure integrated model
Module + steel-structure integrated model

Full Detailed Engineering Drawing Package

Delivered a complete set of construction drawings meeting utility company approval standards, covering PV, structural, and electrical disciplines. Drawing depth satisfies grid interconnection application requirements.

No.Drawing TitlePurpose
1PV Module Layout PlanModule arrangement, string configuration, maintenance corridor planning
2Steel Structure Detail DrawingCanopy frame dimensions, joint connections, load calculations
3Waterproof Mounting DetailWaterproofing node details, drainage design, sealing treatment
4Grid Connection DiagramPV interconnection point, protection configuration, metering scheme
5Electrical Single Line DiagramPrimary system wiring, inverter configuration, distribution scheme
No.1

PV Module Layout Plan

PV Module Layout Plan
PV Module Layout Plan
String numbering and inverter allocation diagram
String numbering and inverter allocation diagram
No.2

Steel Structure Detail Drawing

Steel Structure Detail — section and elevation views
Steel Structure Detail — section and elevation views
No.3

Waterproof Mounting Detail

Waterproof Mounting Detail — node and tile detail
Waterproof Mounting Detail — node and tile detail
No.4

Grid Connection Diagram

Grid Connection Diagram
Grid Connection Diagram
No.5

Electrical Single Line Diagram

Electrical Single Line Diagram
Electrical Single Line Diagram
SECTION III.

Grid Interconnection Approval Support

The project drawings passed utility review on the first submission, with only 60 days from design to grid connection. We understand the technical review focus of grid companies and proactively address interconnection compliance during the drawing design phase, avoiding repeated revisions and schedule delays.

StageScope of WorkDeliverable
Step 1Grid Connection ApplicationSubmit interconnection application and project filing documents
Step 2Drawing Technical ReviewSubmit complete drawing package for technical review
Step 3Drawing Approval ObtainedFirst-pass approval, written approval from utility company
Step 4Power Supply ApplicationSign power supply contract, install metering equipment
Step 5Interconnection PermitObtain formal grid interconnection permit
Step 6Commercial OperationGrid-connected in July 2025, entering commercial operation
Utility Grid Interconnection Approval — approval letters, drawing-review pass certificate, interconnection permit
Utility Grid Interconnection Approval — approval letters, drawing-review pass certificate, interconnection permit
SECTION IV.

Design Highlights

01

BIPV Waterproof Solar Canopy Integration

PV modules serve dual functions of power generation and architectural shading/waterproofing. Steel frame structure validated through load and wind-pressure calculations — adapted to Dongguan's typhoon-prone climate.

02

Bifacial Module High Efficiency

615 Wp bifacial double-glass modules deliver 10% rear-side gain, fully utilizing ground-reflected light in elevated canopy installations.

03

Huawei Smart Inverter Solution

3 × 110 kW string inverters with PLC communication and IV curve diagnosis. 330 kW total inverter capacity scientifically matched with 362 kWp module capacity.

04

Distribution System Compatibility

During the survey phase, we assessed existing distribution-room capacity and cable routing. The interconnection design does not exceed original protection thresholds, ensuring grid safety.

05

First-Pass Drawing Approval

All 5 categories of detailed drawings comply with China Southern Power Grid interconnection standards. Zero revisions from submission to approval — design to grid connection in just 60 days.

06

Rapid Delivery Capability

Design started May 2025, grid-connected July 2025 — validating our EPC execution efficiency from design, procurement and construction through commissioning.

SECTION V.

Construction & Commissioning

From drawing approval to plant completion, we provide full-process technical support. Below are the key construction milestone records:

Steel Structure Installation
Steel Structure Installation
Module & Cable Routing
Module & Cable Routing
Commissioning
Commissioning
SECTION VI.

Yield & Environmental Impact

Based on Dongguan area annual equivalent peak sun hours of ~1,150 h, System PR=83%, bifacial gain of 10%, and module degradation of 0.55%/year:

  • First-Year Yield: 379,683 kWh (~380,000 kWh) — enough to power ~70–90 small-to-medium C&I users annually
  • First-Year CO₂ Reduction: 217 tons — equivalent to the annual carbon absorption of ~12,000 mature trees
  • 25-Year Total Yield: ~8.9 million kWh (factoring in 0.55%/year module degradation)
  • Lifetime CO₂ Reduction: ~5,080 tons
Environmental Impact Infographic
Environmental Impact Overview
SECTION VII.

About SJ Solarhub

SJ Solarhub provides integrated EPC solutions covering PV, energy storage, and EV charging infrastructure for commercial, industrial, and residential clients. With 12 years of deep expertise in the new energy sector, our team holds national-grade new energy design qualifications and electrical engineering construction licenses, having cumulatively completed project designs exceeding 150 MW across China and international markets.

We deliver turnkey solutions from site survey, system design, full detailed drawing package, grid interconnection approval support, equipment procurement, construction, to grid-connection O&M, supporting major global certification systems (IEC / TÜV / CE / SAA / ETL).

Our design team is familiar with the interconnection technical standards of China Southern Power Grid, State Grid, and major overseas utility companies, capable of delivering complete drawing packages that meet local approval requirements, ensuring efficient project progression from design to grid connection.

GET IN TOUCH

Need Similar Design & Grid Approval Support?

Contact us for turnkey solutions from survey, design, drawings to grid interconnection.